PROJECT:
Belknap Research Building ($49,000,000)
SCOPE:
The University of Louisville needed a nanotechnology clean-room
building located within the Belknap Campus.
CHALLENGE:
Vibration studies were conducted at various sites in and around
the campus to select a suitable site. The site selected had an
ambient vibration level of 1780 micro-inches per second (mips).
Based on the site location criteria for nanotechnology buildings,
the site was unsuitable for such research. The world renowned
nanotechnology consulting firm of Colin Gordon & Associates,
retained by the University of Louisville, recommended the building
be built where the ambient level would be a fraction of the
expected performance level. For the convenience of the faculty
members, the University of Louisville insisted on keeping the
building at the selected site and placed the responsibility of the
structural design with our firm.
SOLUTION:
Our firm explored various alternatives to dampen the ambient
vibration through computer finite element modeling. We selected an
appropriate system for the construction of the building. For
certification as a building suitable for nano VC-D, the University
retained the independent consulting firm of Colin Gordon &
Associates. Colin Gordon & Associates rated the building well
within the VC-D class and the building almost meets the next lower
level of VC-E class. This research facility is an excellent
nanotechnology building on a non-nano site. Mission Accomplished!
However our creativity is well hidden and buried beneath the soil.
PROJECT:
Cardiovascular
Innovation Institute ($28,000,000)
SCOPE: The medical community of
Louisville, Kentucky has been a pioneer of innovative solutions in
the treatment heart diseases, including artificial heart implants
and heart assistance devices. It is no wonder that the University
of Louisville has recognized the advancements of these treatments
and taken steps to nurture research for the study and treatment of
heart diseases. The University elected to establish and construct
the Cardiovascular Innovation Institute at its Medical Campus.
CHALLENGE:
The site selected on the Medical Campus was bound on three sides
by existing buildings. To take full advantage of the selected
site, the architectural design called for outer columns to be
located at the perimeter of the existing walls.
SOLUTION:
To accommodate the dead and live loads from the seven floors of
this concrete frame building, our firm designed unique foundation
systems composed of eccentric pile caps with tie-beams. To
accommodate the extreme column loads and to alleviate the stress
concentration in the pile caps, we designed special shear blocks,
which safely transfer the heavy column loads to the tie beams. The
new building is now seamlessly integrated with the existing
buildings on all three sides. Mission Accomplished! Our
creativity, again, is buried deep into the ground.
PROJECT: Marriott Convention Center
Bridge ($2,500,000)
SCOPE:
Generally, elevated walkway bridges are built utilizing piers,
which are shaped like a “Hammer Head” and they are
appropriately called “Hammer Head” piers. These piers are
symmetrical, balanced, and easy to build. However, the piers are
major obstacles, constricting pedestrian pathways on the sidewalks
below the elevated walkways. When the city of Louisville decided
to build an elevated walkway bridge to connect the Marriott Hotel
with the Kentucky International Convention Center, the City
requested that the sidewalk below the elevated walkway be allowed
the maximum unrestricted pathways as possible due to heavy
pedestrian traffic.
CHALLENGE:
“Hammer Head” piers were ruled out for the elevated walkway
bridge between the Marriott Hotel and the Kentucky International
Convention Center since they would severely restrict movement on
the sidewalks below. A design, which would allow pedestrian
traffic flow below the elevated walkway, was required for this
project.
SOLUTION:
Our firm devised a creative solution to the problem and designed a
“Sickle” pier, which resembles the shape of a sickle. The
“Sickle” pier is located against the walls of the existing
structures to support the elevated walkway. Mission Accomplished!
Our creativity, once again is buried deep into the ground.
PROJECT: Clinical and Translation
Research Building ($140,000,000)
SCOPE:
The University of Louisville planned to build a cancer research
building in two phases. However, through tremendous support from
the community, all the funding for both phases was acquired and it
was decided to build both phases for cost effective reasons.
CHALLENGE:
The building length dictated the requirement for an expansion
joint at the most critical area that affects the aesthetics and
interior design of the building. In addition, the expansion joint
would increase the cost of the building.
SOLUTION:
Various alternatives including the use of the expensive type
“K” cement were discussed to minimize the expansion and
contraction during the construction phase. It was finally decided
to leave out an infill strip in the transverse direction to
relieve the thermal stresses during the construction phase and
fill the strip at a later date. This simple solution spared the
requirement for an expansion joint and the associated hardware,
thereby saving thousands of dollars in construction costs. Mission
Accomplished! However, our creativity is latent and preserved for
future generations to investigate.
PROJECT: Lahoff Milling Company,
Danville, Illinois ($35,000,000)
SCOPE:
Lahoff Milling Company decided to expand their corn milling
facility.
CHALLENGE:
Lahoff Milling Company dictated two conditions for the expansion
of their facility to avoid the trapping of the flour dust that has
the potential for becoming a breeding ground for insects. The two
conditions were:
- No
cracking in the concrete slab.
- Other
than the working floor, no member shall have exposed surface
that is less than 60 degrees.
SOLUTION:
The building was seven stories and the team elected to use only
composite steel frame made of steel tubes fabricated in double
cruciform trees and if necessary, wide flange beams with
protective plates to the bottom flange inclined at 60 degrees to
the horizontal surface. The team selected “K” Shrinkage
Compensating Cement for all floor slabs to minimize the surface
cracking. The project was successfully completed to the
satisfaction of the client. Mission Accomplished! Again our
creativity is well preserved in a latent state.
PROJECT: LMPD River Station ($350,000)
SCOPE:
Louisville Metro Police Department decided to construct a River
Station, which is a floating office located on the Ohio River.
CHALLENGE:
The Louisville Metro Police Department was very concerned about
the live load capacity as well as the floatation capability of
their new office building.
SOLUTION:
Our firm made calculations, detailed the necessary floatation
system, which can fully support full dead and live loads imposed
by the Kentucky Building Code and provide the free board necessary
for this floating building. Mission Accomplished! This time our
creativity is sunk in the deep river waters.